January 25, 2012 Board Meeting Information

Board Meeting Power Point Presentation

PROJECT

District School
Bellingham Clara Macy Elementary School
Haverhill Caleb Dustin Hunking Middle School
Milford Woodland Elementary School
Newton A.E. Angier Elementary School
Northborough Lincoln Street Elementary School
North Middlesex North Middlesex Regional High School
Swampscott Hadley Elementary School
Wareham Minot Forest Elementary School
District School Invite Date
Abington Frolio Middle School September 29, 2008
Chelsea Clark Avenue School November 28, 2007
Gloucester West Parish School November 18, 2009
Holbrook Holbrook Junior/Senior High School November 28, 2007
Lunenberg Lunenberg High School November 18, 2009
Minuteman Regional School District Minuteman Career and Technical High School July 29, 2009
Westborough Sarah W. Gibbons Middle School September 30, 2009
  • Recommendation for Preferred Schematic Design
District School Scope Preliminary Design Pricing - Estimated Total Construction Estimated Total Project Budget
Georgetown Penn Brook Elementary School New Walk-in
Lexington Joseph Estabrook Elementary School New  $30,770,743 $42,783,546 
Lincoln Lincoln School Add/Reno  $39,262,188 $49,000,000 
Webster Park Avenue Elementary School  New  $35,040,000 $44,200,000 
West Bridgewater West Bridgewater Middle-Senior High School New $49,068,146 $63,800,00
    Totals  $154,141,077 $199,783,546 
  • Invitation to Project Scope and Budget
District School Scope Total Project Budget Estimated Maximum Total Facilities Grant
Danvers Danvers High School PS&B Adjustment  
Franklin Franklin High School New - Model $104,649,876 $54,558,408
Lynnfield Lynnfield High School Addition $4,500,044 $1,856,512
North Reading North Reading Middle-High School Add/Reno $107,727,074 $47,112,775
Shrewsbury Sherwood Middle School PS&B Adjustment  
Southern Worcester County Regional Vocational School District Bay Path Regional Vocational Technical High School Add/Reno $73,722,405 $44,510,177
Stoneham Stoneham Middle School Add/Reno $40,582,390 $21,235,592
Williamsburg Anne T. Dunphy Elementary School Add/Reno $12,923,689 $6,924,167
    Totals $344,105,478 $176,197,631
  • Capital Pipeline Project Removal
District School Scope Invite Date
Hopkinton Center Elementary School New November 28, 2007
Northeast Metro Regional School District Northeast Metro Regional Vocational High School Renovation July 29, 2009
  • Green Repair Project Removal
District School Scope Invite Date
Haverhill Hunking Middle School Windows November 17, 2010
  Greenleaf Elementary School Roof November 17, 2010

Project Status

AUDIT

District School Scope Total Project Budget Total Facilities Grant
Attleboro Attleboro High School Green Repair $391,778 $221,007
Hopkinton Center Elementary School Feasibility Study $424,211 $169,684
    Totals $815,989 $390,691

FINANCE