DSP Meeting Results:

Meeting Date: December 20, 2011

Ayer – Ayer-Shirley Regional Middle/High School

Application review at the December 6, 2011 DSP meeting and interviews at the December 20, 2011 meeting resulted in the following ranking of applicants:

  1. Symmes Maini & McKee Associates, Inc.
  2. Design Partnership of Cambridge, Inc.
  3. Flansburgh Associates, Inc.

Newburyport – R.A. Nock/E.G. Molin School

Application review at the December 20, 2011 DSP meeting resulted in the following unranked list of applicants:

  • Miller Dyer Spears, Inc.
  • Symmes Maini & McKee Associates, Inc.

There will be interviews for the R.A. Nock/E.G. Molin School at the next scheduled DSP meeting on Tuesday, January 10, 2012.

Auburn – Auburn Middle School

Application review at the December 20, 2011 DSP meeting resulted in the following unranked list of applicants:

  • ARC/Architectural Resources Cambridge
  • Lamoureux Pagano & Associates, Inc.
  • OMR Architects, Inc.

There will be interviews for the Auburn Middle School at the Tuesday, January 24, 2012 DSP meeting.

There were no informational interviews at this meeting.


DSP Meeting Results:

Meeting Date: December 6, 2011

Tyngsboro  – Greater Lowell Technical High School

Application review at the December 6, 2011 DSP meeting resulted in the following ranking of applicants:

  1. Knight, Bagge & Anderson, Inc.
  2. Kaestle Boos Associates, Inc.
  3. Lamoureaux, Pagano & Associates, Inc.

There will not be interviews for this project.

Ayer-Shirley Regional School District – Ayer-Shirley Regional Middle High School

Application review at the December 6, 2011 DSP meeting resulted in the following unranked list of applicants:

  • Design Partnership of Cambridge, Inc.
  • Flansburgh Associates, Inc.
  • Symmes Maini & McKee Associates, Inc.

There will be interviews for the Ayer-Shirley Regional Middle High School at the next scheduled DSP meeting on December 20, 2011.


DSP Meeting Results:

Meeting Date: November 22, 2011

South Hadley – Plains Elementary School

Application review at the November 8, 2011 meeting and interviews at the November 22, 2011 meeting resulted in the following ranking of applicants:

  1. Margo Jones Architects, Inc.
  2. Flansburgh Associates, Inc.
  3. Design Partnership of Cambridge, Inc.

There were no informational interviews at this meeting.


DSP Meeting Results:

Meeting Date: November 8, 2011

South Hadley – Plains Elementary School

Application review at the November 8, 2011 DSP meeting resulted in the following unranked list of applicants:

  • Design Partnership of Cambridge, Inc.
  • Flansburgh Associates, Inc.
  • Margo Jones Architects, Inc.

Interviews for the Plains Elementary School will be held at the next DSP meeting on Tuesday, November 22, 2011.

There were informational interviews with the following firms at this meeting:

  • Fitzmeyer & Tocci Associates, Inc.
  • New Vista Designs
  • id3A, LLC

DSP Meeting Results:

Meeting Date: October 4, 2011

Greater New Bedford Regional Vocational Technical High School

Application review at the September 20, 2011 DSP meeting and interviews at the October 4, 2011 DSP meeting resulted in the following ranking of applicants:

  1. Drummey Rosane Anderson, Inc.
  2. Kaestle Boos Associates, Inc.
  3. Miller Dyer Spears, Inc.

Boston – Quincy Upper School

Application review at the October 4, 2011 DSP meeting resulted in the following ranking of applicants:

  1. HMFH Architects, Inc.
  2. Finegold Alexander and Associates, Inc.
  3. Fletcher Thompson Architecture Engineering, LLC

There were no informational interviews at this meeting.


DSP Meeting Results:

Meeting Date: September 20, 2011

Greater New Bedford Regional Vocational Technical High School

Application review at the September 20, 2011 DSP meeting resulted in the following unranked list of applicants:

  • Drummey Rosane Anderson, Inc.
  • Kaestle Boos Associates, Inc.

There were informational interviews with the following firms at this meeting:

  • ARC/Architectural Resources Cambridge

Interviews for the Greater New Bedford Regional Vocational Technical High School will be held at the next DSP meeting on Tuesday, October 4, 2011.


DSP Meeting Results:

Meeting Date: September 13, 2011

Lexington – Joseph Estabrook Elementary School

Application review at the August 23, 2011 DSP meeting and interviews at the September 13, 2011 DSP meeting resulted in the following ranking of applicants:

  1. DiNisco Design Partnership, Limited
  2. Symmes Maini & McKee Associates, Inc.
  3. Mount Vernon Group Architects, Inc.

There were informational interviews with the following firms at this meeting:

  • Cambridge Seven Associates, Inc.
  • SAR Engineering, Inc.

DSP Meeting Results:

Meeting Date: August 23, 2011

West Bridgewater – Middle-Senior High School

Application review at the August 2, 2011 DSP meeting and the interviews at the August 23, 2011 DSP meeting resulted in the following ranking of applicants:

  1. Flansburgh Associates, Inc.
  2. Design Partnership of Cambridge, Inc.
  3. Finegold Alexander and Associates, Inc.
  4. HMFH Architects, Inc.

Lexington – Joseph Estabrook Elementary School

Application review at the August 23, 2011 DSP meeting resulted in the following unranked list of applicants:

  • DiNisco Design Partnership, Limited
  • Symmes Maini & McKee Associates, Inc.

Interviews for the Lexington Joseph Estabrook Elementary School will be held at the next DSP meeting on Tuesday, September 13, 2011.

Webster – Park Avenue Elementary School

Application review at the August 23, 2011 DSP meeting resulted in the following ranking of applicants:

  1. Dore & Whittier Architects, Inc.
  2. Taylor & Burns, Inc.
  3. Kaestle Boos Associates, Inc.

There were no informational interviews at this meeting.


DSP Meeting Results:

Meeting Date: August 2, 2011

West Bridgewater – Middle-Senior High School

Application review at the August 2, 2011 DSP meeting resulted in the following unranked list of applicants:

  • Design Partnership of Cambridge, Inc.
  • Finegold Alexander and Associates, Inc.
  • Flansburgh Associates, Inc.
  • HMFH Architects, Inc.

The interviews for the West Bridgewater Middle-Senior High School project will be held at the next DSP meeting on Tuesday, August 23, 2011.

There were also informational interviews with the following firms:

  • BVH Integrated Services
  • Taylor & Burns, Inc.
  • The Arch Professional Group, Inc.

DSP Meeting Results:

Meeting Date: July 19, 2011

Wakefield – Galvin Middle School

Application review at the July 19, 2011 DSP meeting resulted in the following ranking of applicants:

  1. Tappé Associates, Inc.
  2. Drummey Rosane Anderson, Inc.
  3. Mount Vernon Group Architects, Inc.

Georgetown – Penn Brook School

Application review at the July 19, 2011 DSP meeting resulted in the following ranking of applicants:

  1. Drummey Rosane Anderson, Inc.
  2. Flansburgh Associates, Inc.
  3. Dore & Whittier Architects, Inc.

There were also informational interviews with the following firms:

  • Schwartz/Silver Architects, Inc.
  • The S/L/A/M Collaborative, Inc.

DSP Meeting Results:

Meeting Date: April 19, 2011

North Reading – North Reading Middle/High School

Application review at the April 19, 2011 DSP meeting resulted in the following ranking of applicants:

  1. Dore & Whittier Architects, Inc.
  2. Flansburgh Associates, Inc.
  3. Tappé Associates, Inc.

There were also informational interviews with the following firms:

  • Perry Dean Rogers & Partners Architects, Inc.
  • Lindgren & Sharples, P.C.

Meeting Date: March 15, 2011

Peabody – Higgins Middle School

Application review at the February 15, 2011 DSP meeting and finalist interviews at the March 15, 2011 DSP meeting resulted in the following ranking of applicants:

1.    DiNisco Design Partnership, Limited
2.    Mount Vernon Group Architects, Inc.
3.    Kaestle Boos Associates, Inc.

Greenfield – Greenfield High School

Applications review at the March 15, 2011 DSP meeting resulted in the following ranking of applicants:

1.    Dore & Whittier Architects, Inc.
2.    Symmes Maini & McKee Associates, Inc.
3.    The S/L/A/M Collaborative

There were no informational interviews at this meeting.

 


 

Meeting Date: March 1, 2011

Stoneham – Stoneham Middle School 

Application review at the February 15, 2011 DSP meeting and interviews at the March 1, 2011 DSP meeting resulted in the following ranking of applicants:

  1. Tappé Associates, Inc.
  2. Drummey Rosane Anderson, Inc.
  3. Mount Vernon Group Architects, Inc. and Raymond Design Associates, Inc. (tied)

Williamsburg – Ann T. Dunphy School

Application review at the March 1, 2011 DSP meeting resulted in the following ranking of applicants:

  1. Drummey Rosane Anderson, Inc.
  2. JCJ Architecture, PC
  3. Fletcher Thompson Architecture Engineering, LLC

There were no informational interviews at this meeting. 

 


 

Meeting Date: February 15, 2011

Concord-Carlisle - Concord-Carlisle High School

Application review at the February 15, 2011 DSP meeting resulted in the following ranking of applicants:

  1. OMR Architects, Inc.
  2. Lavallee Brensinger Architects
  3. ARCADD, Inc.

Wilmington – Wilmington High School

Application review at the February 15, 2011 DSP meeting resulted in the following ranking of applicants:

  1. Dore & Whittier Architects, Inc.
  2. Symmes Maini & McKee Associates, Inc.
  3. Flansburgh Associates, Inc.

Peabody – J. Henry Higgins Middle School

Application review at the February 15, 2011 DSP meeting resulted in the following unranked list:

  • DiNisco Design Partnership, Limited
  • Kaestle Boos Associates, Inc.
  • Mount Vernon Group Architects, Inc.

Interviews for the Peabody Higgins Middle School project have not yet been scheduled.

Stoneham – Stoneham Middle School

Application review at the February 15, 2011 DSP meeting resulted in the following unranked list:

  • Drummey Rosane Anderson, Inc.
  • Tappé Associates, Inc.

Interviews for the Stoneham Middle School project have not yet been scheduled.

There were no informational interviews at this meeting.

 


 

Meeting Date: January 11, 2011

Lincoln - Lincoln School

Application review at the December 7, 2010 DSP meeting and interviews at the January 11, 2011 DSP meeting resulted in the following ranking of applicants:

  1. OMR Architects, Inc.
  2. Symmes Maini McKee Associates, Inc.

Saugus - Belmonte Middle School

Application review and interviews at the January 11, 2011 DSP meeting resulted in the following ranking of applicants:

  1. Fletcher Thompson Architecture Engineering, LLC
  2. Mount Vernon Group Architects, Inc.

There were no informational interviews at this meeting.

 

 

 

DSP Meeting Results:

Meeting Date: July 19, 2011