Board Meeting PowerPoint Presentation
District |
School |
Whittier Regional Vocational Technical School District |
Whittier Regional Vocational Technical High School |
District |
School |
Blackstone-Millville |
Blackstone-Millville Regional High School |
Marlborough |
Richer Elementary School |
Wrentham |
Charles E. Roderick School |
- Recommendation for Preferred Schematic Design – Vote
District |
School |
Scope |
Estimated Total Construction |
Estimated Total Project Costs |
William H. Galvin Middle School |
New |
$186,224,907 |
$232,781,134 |
|
South Shore Regional Technical High School |
New |
$225,773,834 |
$283,595,433 |
|
Total |
$411,998,741 |
$516,376,567 |
- Invitation to Project Scope and Budget: Estimated Maximum Total Facilities Grants of $391,756,510 - Vote
District |
School |
Scope |
Total Project Budget |
Estimated Maximum Total Facilities Grant |
Clinton Middle School |
New |
$139,520,548 |
$75,710,410 |
|
Revere High School |
New |
$497,517,901 |
$233,889,807 |
|
Hatherly Elementary School |
New |
$119,434,943 |
$35,134,823 |
|
South Elementary School |
New |
$114,407,877 |
$47,021,470 |
|
Total |
$870,881,269 |
$391,756,510 |
Audit
- Audit Status Report
- Approval of Final Audits with no appeals, MSBA Capital Pipeline Projects grants of $1,215,824- Vote
District |
School |
Scope |
Total Project Budget |
Total Facilities Grant |
Blackstone-Millville |
Millville Elementary |
Accelerated Repair |
$1,807,687 |
$890,339 |
Cambridge |
Fletcher/ Maynard Academy |
Accelerated Repair |
$1,057,523 |
$325,485 |
Total |
$2,865,210 |
$1,215,824 |
MSBA Updates
- Executive Director Report
- Project Status
Finance
Legal
Executive Session