District Presentations
The following district presented on the progress of their proposed project at the July 15, 2026 Massachusetts School Building Authority (the “MSBA”) Facilities Assessment Subcommittee (the “FAS”) Meeting:
District: City of Medford
School: Medford High School
Phase: Feasibility Study
Owner’s Project Manager: LeftField, LLC
Designer: Symmes Maini & McKee Associates, Inc.
The City of Medford (the “District”), the Owner’s Project Manager, and design team presented an overview of the options studied during the Feasibility Study and the District’s preferred solution to proceed into Schematic Design for an addition/renovation of the existing Medford High School for grades 9-12. The FAS, MSBA staff, and the District discussed the following:
- Site topography, constraints and overall complexity of the Proposed Project;
- Inclusion of specialized programming including substantially separate Special Education programs and clarification of proposed distribution and adjacencies;
- DESE review of the Special Education submission following Schematic Design;
- Appreciation for the District’s Educational Program and its goals of integrating CTE and additional program elements into a unified high school, as well as the updates made since the original submission;
- Opportunity to use the proposed construction duration to maximize professional development, staff engagement and teacher planning time;
- Suggestion to consider interdisciplinary learning opportunities, particularly for second-semester seniors to engage in seminars or exploratory projects;
- Appreciation for the overall building design and organization, including the location of music spaces in relation to the existing gym, the main entry courtyard and smaller rear courtyards;
- Opportunity to enhance the visibility of the auditorium entrance;
- Interior circulation and vertical connectivity between the proposed Dining Commons and Media Center;
- The view of the building upon approach and the proposed parking area;
- Variations from MSBA space guidelines associated with proposed District administration and community spaces and considerations for the Schematic Design phase;
- The proposed construction schedule and logistics as well as the importance of forecasting construction costs;
- Potential locations of geothermal wells on the site;
- Clarification of the location and number of proposed elevators; and,
- Building geometry, orientation, and design considerations associated with preserving the building area proposed for renovation.
Staff Presentations:
- Staff presented on the following items at the July 15, 2026 Facilities Assessment Subcommittee meeting:
- Schematic Design Updates
- Blackstone-Millville, Blackstone-Millville Regional High School
- Chicopee, Anna E. Barry Elementary School
- Review of Core Project Funding Limits
- 2026 Core Program Further Review Recommendations
- Model School Procurement Update