The following districts presented on the progress of their proposed projects at the July 29, 2026 Massachusetts School Building Authority (the “MSBA”) Facilities Assessment Subcommittee (the “FAS”) Meeting:
District: Town of Northborough
School: Marguerite E. Peaslee Elementary School
Phase: Feasibility Study
Owner’s Project Manager: PMA Consultants, LLC
Designer: Flansburgh Associates, Inc.
The Town of Northborough (the “District”), the Owner’s Project Manager, and design team presented an overview of the options studied during the Feasibility Study and the District’s preferred solution to proceed into Schematic Design to replace the existing Marguerite E. Peaslee Elementary School with a new facility serving students in Kindergarten through grade 5, plus Pre-Kindergarten, on the site of the existing school. The FAS, MSBA staff, and the District discussed the following:
- Appreciation of the District’s Educational Program and the updates made since the original submission;
- Distribution of Special Education spaces and the DESE review process following Schematic Design;
- Appreciation for the flexibility of the proposed general classrooms for multidisciplinary learning as well as the inclusion of professional librarian services, dedicated professional support and space for Digital Literacy and Computer Science instruction;
- Potential opportunities for the design team to showcase sustainability elements such as energy and water use as design features and as part of community outreach for the Proposed Project;
- The importance of continued input from faculty and staff as the design progresses;
- Appreciation for the overall building design;
- Building massing and scale;
- Proposed parking locations; and,
- Roof design considerations as it relates to architectural features as well as the location of mechanical equipment and photovoltaic panels.
District: Town of South Hadley
School: Mosier Elementary School
Phase: Feasibility Study
Owner’s Project Manager: Skanska USA Building. Inc.
Designer: Mount Vernon Group Architects, Inc.
The Town of South Hadley (the “District”), the Owner’s Project Manager, and design team presented an overview of the options studied during the Feasibility Study and the District’s preferred solution to proceed into Schematic Design to replace the existing Mosier Elementary School with a new facility serving grades 1 through 5 on the site of the existing school. The FAS, MSBA staff, and the District discussed the following:
- The District’s Educational Program and previous feedback communicated as part of MSBA review of the Preliminary Design Program regarding proposed scheduling as it relates to the implementation of project-based learning, use of the proposed STE room, and proposed professional development opportunities;
- Appreciation for the building design concept that incorporates entry into a large forecourt with two wings;
- Suggestion to consider plantings and opportunities to extend green space between the building and proposed parking area;
- Opportunity for transparency and visual connection from the building entry to the cafeteria; and,
- Distribution and location of Special Education classrooms, particularly those proposed at the end of hallways in classroom neighborhoods, and the DESE review process associated with the Schematic Design submission.
District: Town of Needham
School: Pollard Middle School
Phase: Schematic Design
Owner’s Project Manager: Town of Needham
Designer: HMFH Architects, Inc.
The Town of Needham, the Owner’s Project Manager, and design team presented an update on the progress of the Pollard Middle School project since submission of the District’s Preferred Schematic, providing an overview of the development, modifications and refinement of the overall building design and layout. The FAS, MSBA staff, and the District discussed the following:
- Appreciation for the thoughtful changes and refinements to the design since the submission of the District's Preferred Schematic;
- Reductions in the estimated project cost since the Preferred Schematic Report and the associated factors;
- Considerations for the location of parking;
- Refinements to the proposed entrance to the site and improvements to pedestrian experience;
- Rationale for incorporating a purple roof as a construction add-alternate compared to the base scope of a green roof;
- Importance of ongoing community outreach; and,
- Construction phasing schedule and intentions.