The following districts presented on the progress of their proposed projects at the September 30, 2026 Massachusetts School Building Authority (the “MSBA”) Facilities Assessment Subcommittee (the “FAS”) Meeting:
District: City of Somerville
School: Winter Hill Community School
Phase: Feasibility Study
Owner’s Project Manager: PMA Consultants, LLC
Designer: Perkins Eastman
The City of Somerville (the “District”), the Owner’s Project Manager, and design team presented an overview of the options studied during the Feasibility Study and the District’s preferred solution to proceed into Schematic Design for a project that proposes to consolidate the student population of the Winter Hill Community School and Benjamin G. Brown Elementary School and construct a new facility serving Kindergarten though grade 8, plus Pre-Kindergarten, on the site of the existing Winter Hill Community School. The FAS, MSBA staff, and the District discussed the following:
- Appreciation of the thoroughness of the District’s Educational Program, especially regarding the diversity in programming to meet the needs of various learners;
- Scheduling considerations, specifically the complexity of offerings;
- The distribution of Special Education spaces and the DESE review process during Schematic Design;
- Opportunities for after school programs and accessibility for all families;
- Clarity on the various entry points throughout the building;
- Site constraints and topography and associated massing and elevation considerations;
- The importance of plans for the maintenance of the rooftop and outdoor spaces;
- Ongoing cost considerations; and,
- Appreciation for the focus on incorporating daylight throughout the building as the design progresses.
District: City of Springfield
School: German Gerena Community School
Phase: Feasibility Study
Owner’s Project Manager: Skanska USA Building, Inc.
Designer: DiNisco Design, Inc.
The City of Springfield (the “District”), the Owner’s Project Manager, and design team presented an overview of the options studied during the Feasibility Study and the District’s preferred solution to proceed into Schematic Design to replace the existing German Gerena Community School with a new facility on the Chestnut Street site. The FAS, MSBA staff, and the District discussed the following:
- Appreciation of the District’s Educational Program and accompanying revisions, specifically regarding comprehensive professional development for non-teaching staff, the inclusion and use of the Planetarium, use of the Media Center, and dual-language programs;
- The distribution of Special Education spaces and the DESE review process during Schematic Design;
- Potential to include a spring floor for the dedicated dance classroom;
- Consideration of incorporating Science and Social Studies as part of the allotted instructional time for English Language Arts;
- Benefits of looping for young learners;
- Appreciation of the overall design and massing;
- Suggestion to refine visual aids for community outreach;
- Use of sectional relationships within the proposed building; and,
- Stormwater management and drainage on site.
District: Town of Leicester
School: Leicester High School
Phase: Schematic Design
Owner’s Project Manager: TERVA Corporation
Designer: Raymond Design Associates, Inc.
The Town of Leicester, the Owner’s Project Manager, and design team presented an update on the progress of the Leicester High School project since submission of the District’s Preferred Schematic, providing an overview of the development, modifications and refinement of the overall building design and layout. The FAS, MSBA staff, and the District discussed the following:
- Clarification of the four buildings included within the scope of the MSBA project
- The District’s future plans for the Winslow Building and Gymnasium, including any potential minor improvements, use as swing space during construction, introduction of future Chapter 74 programs, and the relocation of the Chapter 74 Early Education and Care Program from the Winslow building to the Swan building;
- The anticipated DESE review of Special Education spaces;
- Impact on operational costs of managing multiple buildings;
- Renovation and partnership plans at the Fuller building; and,
- Accessibility at the Swan building, including the recommendation to consider a canopy.
Staff Presentations:
Staff presented on the following item at the September 30, 2026 Facilities Assessment Subcommittee meeting:
- Space Summary Phase 3 Preview
Meeting Materials