Module 2 – Forming the Project Team

Once all of the Pre-Requisites have been completed to the satisfaction of the MSBA, the District procures the team of professionals utilizing MSBA specific procurement processes and standard Request for Services (“RFS”) templates and Contracts to work with the District as the proposed project advances through the MSBA’s grant process.


Core Program:
 
Since the January 27, 2016 Board Meeting:

  • Three Districts have completed their OPM selection (Boston, Cape Cod Regional, Easthampton)
  • One District has completed its Designer Selection (Saugus)
As of the March 30, 2016 Board Meeting:

14 Districts are currently procuring professional services:
  • 10 Districts are in the process of procuring an Owner's Project Manager (Attleboro, Bristol County Agricultural, Clarksburg, Everett, Fall River, Holyoke, Lowell, Middleborough, Taunton, Worcester)
  • Four Districts are in the process of procuring a designer (Boston, Lynn, Waltham, Westport)