MSBA Approves over $12.6M in Accelerated Repair Grants

Expedited Process Improves Learning Environments for Children in 10 Schools

BOSTON - State Treasurer Deborah B. Goldberg, Chair of the Massachusetts School Building Authority ("MSBA"), and Jack McCarthy, MSBA Executive Director/Deputy CEO, announced today that the MSBA Board of Directors has approved up to $12,665,919 for 10 Accelerated Repair Projects in 9 school districts.
"The Accelerated Repair Program allows us to make critical repairs to more schools in less time," said Treasurer Deborah B. Goldberg. "By improving the learning environment for our children, the Program also makes schools more energy efficient and generates significant cost savings."

The main goals of the Accelerated Repair Program are to improve learning environments for children and teachers, reduce energy use, and generate cost savings for districts. The program provides funding for the repair or replacement of roofs, windows, and boilers in schools that are otherwise structurally, functionally, and educationally sound.

"The MSBA continues to partner with Massachusetts communities in the ongoing work of upgrading their public schools," Executive Director/Deputy CEO McCarthy said. "These improvements to school facilities can only enhance students' ability to excel in the classroom."

Below is a list of the projects that were approved for Accelerated Repair Program grants at the Board meeting today:

District School Scope Total Project Budget Estimated Maximum Total Facilities Grant
Cambridge Graham and Parks School Roof $4,025,017 $1,598,765
Danvers Highlands Elementary School Roof $3,244,746 $1,561,120
Lynn Lynn Vocational Technical Institute Partial Roof $4,237,788 $2,620,706

Nashoba Valley Technical School District

Nashoba Valley Technical High School

Partial Roof, Partial Windows/Doors $3,704,616 $1,572,132
New Bedford John A. Parker Elementary School Roof $1,450,861 $1,057,879
Trinity Day Academy Boilers $816,107 $627,348
Newton Bigelow Middle School Boilers $1,364,006 $398,234
Norfolk H. Olive Day School Roof $2,890,801 $1,066,359
Springfield Milton Bradley School Partial Roof $3,356,488 $1,942,410
West Bridgewater Howard Elementary School Partial Roof $447,068 $220,966
    Totals $25,537,498 $12,665,919

The MSBA partners with Massachusetts communities to support the design and construction of educationally-appropriate, flexible, sustainable, and cost-effective public school facilities. Since its 2004 inception, the Authority has made over 1,750 site visits to more than 250 school districts as part of its due diligence process and has made over $13.6 billion in reimbursements for school construction projects.