After successfully completing Module 1, the District enters Module 2 where it forms the team that will make its way through the MSBA pipeline throughout the rest of the building process.
Overview
In this Module, the District procures the team of professionals utilizing MSBA-specific procurement and standard Request for Services (RFS) templates and contracts. The team of professionals the District procures are the Owner’s Project Manager (OPM) and the designer.
Recent News
As of the December 12, 2025 Board Meeting:
Eleven districts were in the process of procuring professional services:
- Four districts were in the process of procuring an Owner’s Project Manager:
- Worcester, Burncoat Senior High School
- Haverhill, John G. Whittier Middle School
- Triton RSD, Triton Regional High School
- Peabody, Veterans Memorial High School
- Seven districts were in the process of procuring Designer services:
- Dighton-Rehoboth, Dighton Elementary School
- New Bedford, Charles S. Ashley Elementary School
- Framingham, Hemenway Elementary School
- Milford, Milford High School
- Boston, Pauline Agassiz Shaw Elementary School
- Everett, Everett High School
- Westford, Col. John Robinson Elementary School