Module 7 Schedule Activities

The schedule activities enumerated below must be carried on the project schedule beginning within two weeks of the District’s approval of the General Contractor’s or Construction Manager’s construction schedule. These schedule activities are required in addition to the schedule activities required by Module 4 – Schematic Design, Section 4.1.2, and the project schedule should continue to carry all schedule activities required by Module 4. This project schedule must be kept up-to-date and submitted to the MSBA monthly with the OPM Report.

  • Punch list start and end dates;
  • Date of project registration with US Green Building Council (“USGBC”) or Collaboration for High Performance Schools (“CHPS”);
  • Provisional / Design package submittal date to USGBC or CHPS;
  • Submittal date of 50% DCAMM Notification and 100% DCAMM Notification;
  • General Contractor / Construction Manager request for final payment;
  • Commissioning consultant inspection (substantial completion plus approximately ten months);
  • Submittal date of Final Commissioning Report to MSBA;
  • Submittal date of Final / Construction package including but not limited to Final Commissioning Report to USGBC or CHPS;
  • Anticipated issuance date of final Green School Program Certification letter from USGBC or CHPS;
  • Submittal date to MSBA of Commissioning Certificate of Completion;
  • Submittal date to MSBA of final reimbursement request.